NFL plans to avoid Super Bowl power problems of ’13

NFL plans to avoid Super Bowl power problems of ’13

POWER PLAY: The 2013 Super Bowl was delayed for more than a half-hour due to power problems that left much of the stadium in the dark. Photo: Associated Press

EAST RUTHERFORD, N.J. (AP) — With the memory of last February’s Super Bowl power outage front and center, officials have laid out plans for how they plan to avoid a similar problem at MetLife Stadium in February.

The head of Public Service Electric & Gas says the utility is running a third power line into the electrical substation at the Meadowlands sports complex.

PSE&G president Ralph LaRossa said Thursday that even if two of the power lines fail, the third would be enough to power the complex.

LaRossa said the Super Bowl site will require about 18 megawatts of electricity, or about what it takes to power 12,000 homes.

A partial power outage that caused a 34-minute delay at the Superdome was blamed on an electrical relay device installed specifically to prevent a power failure.

What's On 'KLH?

Hire Me MKE

HireMeMKE_620x400

Looking for a job around the Milwaukee area? Check out some openings>>

Wanna Play DJ?

HEYMOM

You can host your own show Sunday night at 6 on ‘KLH!

Recent Headlines

in Music

Bush needs fans to help fund new album

Fresh
gavinrossdale

Gavin Rossdale and his bandmates have launched a campaign to fund the new album on PledgeMusic.

in Music

Buddy Holly country tribute features song he never recorded

Fresh
holly

Merle Haggard, T. Graham Brown and Jimmy Fortune are among the stars who have covered Holly for new album.

in Entertainment

‘Game of Thrones’ star is ‘strongest man’

Fresh
game

The man who plays Gregor "The Mountain" Clegane is Europe's "Strongest Man."